Solarpark Forst

Completion: 08.12.2011 Const. period: 4 weeks Sub structure: Haticon

plant performance: 3,7 MW Modulecount: 15.708 Moduletype: CSI 235 Wp

Solarpark Göttingen

Completion: 21.12.2011 Const. period: 2 weeks Sub structure: MAGNA

plant performance: 3 MW Modulecount: 12.768 Moduletype: Tianwei

Solarpark Briest

Completion: 09.12.2011 Const. period: 7 weeks Sub structure: MAGNA

plant performance: 91 MW Modulecount: 391.304 Moduletype: Q-Cells

Dachanlage Gingen II

Completion: 30.09.2011 Const. period: 1 weeks

plant performance: 0,19 MW Modulecount: 812

Dachanlage Gingen

Completion: 23.09.2011 Const. period: 2 weeks Sub structure: Knubix

plant performance: 0,11 MW Modulecount: 454 Moduletype: Yingli YL240P

Solarpark Somerset

Completion: 30.07.2011 Const. period: 1 weeks Sub structure: Conergy

plant performance: 0,05 MW Modulecount: 0 Moduletype: Comergy